Construction Contract for Building
|
|
Building contracts for construction of
buildings are governed by the Contract Act. In Building
Agreement, the Party called the Contractor agrees to carry out
work for the other party who is generally the owner of the
plot/land on which the work is to be carried out. The nature of
work may be that of new construction, addition and alteration to
existing building or demolition of building. The owner or a
person who wants to get the building constructed invites tenders
for carrying out the work on the terms and conditions stated in
tender papers, by inserting an advertisement in the newspapers
and accepts the offer of the tenderer considered suited for
carrying out the work having regards to the financial status of
the tenderer, rates quoted by the tenderer, past experience in
carrying out similar type of work, technical staff employed,
tools, plants and machinery owned and time taken to complete the
works. It is not necessary that only lowest tender should be
accepted by the person calling tender. The submission of tender
by the tenderer is an offer. The contract between the two
parties comes into effect on acceptance of the offer of the
tenderer by the Party inviting tenders. The contract papers
consists of description of site, description of proposed work,
all the terms and conditions of contract, estimated
rates/amounts, specifications, quantities, drawings and plans,
basis of consideration (lump sum contract, item rate contract,
percentage rate contract), earnest money required to be made by
tenderer along with tenderer, stipulated time of completion.
General conditions of a building contract covers description of
work to be executed, estimated quantities and rates payable,
payment of earnest money and method of payment of running bills,
time allowed for completion of the work, provision for extension
of time, issuing intention and final Certificate by the
Architect, submission of interior bills by contractor and their
payment, description of materials to be supplied by the owner,
alterations, additions and omissions to be made if required
according to the directions of Architect/ Engineer-in-Charge,
inspection of works, quality control and standard of acceptance,
payment of damages or penalty on failure to commence work,
penalty for delay in completing work, provisions for enforcement
of labour laws, settlement of disputes. In any building contract
certain words, terms appear which have special meaning such as
Architect, Engineer, Contractor, Estimated Cost, Schedule of
rates, specifications, bill of quantities, clerk of works,
Quality Surveyor, Sub-Contractor. As per section 194 C of the
Income-tax Act, 1961 it is the responsibility of the owner to
deduct tax at source at the prescribed rate at the time every
payment is made to the Contractor. As per Article 366 of the
Constitution of India, the States are empowered to levy tax on
sale and purchase of goods in works contract. Payment of Wages
Act, 1936, Workmen’s Compensation Act, 1923, Minimum Wages Act ,
Municipal Act and Contract Labour Act, 1970 are also relevant in
a building Contract. Building or construction contract does not
involve any transfer of any interest in the property and falls
under the general category of agreements under Article 5(c) of
Indian Stamp Act and Article 5(h) of the Schedule I of the
Bombay Stamp Act, 1958. A building contract is not required to
be registered under the Registration Act, 1908 since it doesn’t
involve any transfer of an immovable property in favour of the
Contractor.
A specimen form of construction contract for
building is given hereunder:
Construction Contract for building
THIS AGREEMENT is made at________________________________
this __________day of______________
BETWEEN
___________________________registered under the Companies
Act, 1956, and having its registered office at
__________________________________ hereinafter referred to as
‘the Company’ of the One Part
AND
M/s
______________________________________________________________a
partnership firm consisting of
(1)_____________________ (2)_____________________
(3) __________________ as partners and having their office at
_____________ hereinafter referred to as ‘the Contractors’
of the Other Part.
WHEREAS: –
-
The Company proposes to construct a
building and other structures for running a factory for
manufacturing ............
-
The Company invited tenders and after
examining the several tenders received, the Company has agreed
to accept the tender of the Firm.
-
It is proposed to enter into a regular
contract recording the terms and conditions agreed upon
between the parties.
NOW IT IS AGREED BETWEEN THE PARTIES HERETO
AS FOLLOWS
-
Appointment of Contractors : The
Company hereby appoints the said M/s. XY & Co. as Contractors
to carry out the work of construction of a factory building on
the plot of land belonging to the Company and situate at
________________ admeasuring about ____________ sq. metres and
bearing Survey No ________ and the Contractors agree to carry
out the work of construction hereinafter mentioned on the
terms and conditions hereinafter appearing.
-
Scope of work : The said work of
construction shall consist of constructing and otherwise
completing in all respects a building and appertaining or
incidental structures on the said plot of land in accordance
with (i) the plans hereto annexed marked appendix A and which
are approved by the municipal Corporation and all authorities
concerned including the Town Planning Authority, the
authorities under the factory laws, Fire Brigade authorities
etc., (ii) the specifications and bills of quantities and
schedule of rates mentioned in Appendix B hereto annexed,
(iii) the detail items of work of quantities mentioned in
Appendix ‘C’ hereto annexed, (iv) the conditions contained in
the commencement Certificate issued by the Municipal
Corporation and on the conditions on which the plans are
approved, (v) the detail drawings to be furnished by the
Architect to the Contractors from time to time (vii) the rules
and regulations laid down by the said Municipal Corporation
and other authorities regarding construction of any building,
(viii) the terms and conditions hereinafter mentioned
liability period, date of possession, date of completion etc.
-
This contract sole depository : This
Contract or agreement shall be considered as the sole
depository of the terms and conditions agreed upon between the
parties hereto regarding the carrying out of the said works
and the documents being the invitation to tender, tender and
subsequent correspondence and other papers previous to this
contract will not be looked into for any inference, meaning or
otherwise except where any of the terms of contract is found
to be vague or ambiguous.
-
Cost of work : This cost of
construction payable to the contractors by the company will be
calculated and ascertained on the basis of the actual quantity
of work done at the rates mentioned in the Schedule or rates
hereto attached together with all other amounts payable to the
Contractor under the terms of this contract, less the
deductions authorised to be made by the terms of the contract
as will be certified by the Architect in his final bill.
-
Architect : The term "the Architect"
in this agreement shall mean Mr. ____ _________________ and in
the event of his ceasing to be the architect for the purpose
of this contract, for any reason, such other person as the
Company shall nominate for that purpose, PROVIDED
ALWAYS that, any person subsequently appointed to be the
architect under this contract shall be bound to accept any
certificate or opinion or decision or approval or instruction
given or expressed by the previous Architect for the time
being.
-
Contractors to observe Architect’s
instructions : The Contractors shall forthwith comply with
all instructions issued to them by the Architect in regard to
any matter in respect of which the Architect is expressly
empowered by these conditions to issue instruction. If within
7 days after receipt of a written notice from the Architect
requiring compliance with any instruction the Contractors do
not comply therewith, then the Company may employ and pay
other persons to execute any work whatsoever which may be
necessary to give effect to such instructions and all costs
incurred in connection with such employment shall be
recoverable from the Contractors by the company as a debt or
may be deducted by the company from any monies due or to
become due to the Contractors under this contract.
-
Instruction to be in writing : All
instructions issued by the Architect shall be issued in
writing. If any instruction is issued orally it shall be
confirmed in writing by the Architect or the Company within 7
days and if not denied in writing by the Contractors or the
Architect within three days from the receipt thereof the
confirmation shall be taken as effective as if the instruction
was given in writing.
-
Custody of drawings etc. :
All the drawings and other document mentioned in clause 2
above will remain in the custody of the Architect so as to be
available at all reasonable times for the inspection of the
Company or of the Contractors. However, the Architect shall
furnish to Contractors copies of such of the said documents as
will be required by the Contractors free of costs, provided
that, upon final payment of the contractors’ bill, the
Contractors shall if so requested by the Architect, forthwith
return to the Architect all drawings, details, specifications,
the Schedules and other documents of a like nature referred to
in clause 2 above.
-
Document not o be disclosed elsewhere :
None of the documents hereinbefore mentioned shall be used by
the Contractors for any purpose other than this contract and
neither the Company, the Architect nor the quantity surveyor
shall disclose the same except for the purpose of this
contract in any of the contract bills.
-
No variation without notice to Architect
: The Contractors before making any variation from the
contract drawings or the contract specifications necessitated
by any rules or regulations of the Government or local
authority or any written notice received by such authorities
shall give to the Architect a written notice specifying and
giving the reason for such variation and the Architect may
issue instructions in regard thereto. If within 7 days of
having given the said written notice the Contractors do not
receive any instructions in regard to the matters therein
specified, they shall proceed with the work conforming to the
rules, regulations, or notices in question and any variation
thereby necessitated shall be deemed to be a variation
required by the Architect.
-
Contractors to pay all taxes : The
Contractors shall pay all taxes legally payable in
respect of the said work and shall indemnify and keep
indemnified the Company against any liability of account
thereof.
-
Materials to be according to
specification : All materials, goods and workmanship shall
so far as procurable be of the respective kinds and standards
described in the specification.
-
Powers of the Architect : The
Architect shall have the following powers and the Contractors
will be bound by the exercise of such powers by the Architect.
-
The Architect shall decide any levels
which may be required for the execution of the works and
shall furnish to the Contractors accurate dimensional
drawing and such other information as shall enable the
Contractors to do the work from the ground level.
-
The Architect may issue instructions
requiring the Contractors to open up any work carried out
for inspection and the cost of such opening up any work
carried out and making it good shall be added to the
contract sum unless the work carried out was not in
accordance with the terms of this contract in which case the
cost of re-opening will be on account of the Contractors.
-
The Architect may also issue instructions
for carrying out test of any material or goods, either used
in the work or to be used and the cost of such testing and
of making or substituting any defective material or goods by
proper material or goods will be borne by the Contractors.
-
The Architect may issue instructions in
regard to the removal from the site of any work, material or
goods which do not comply with the requirements of this
contract.
-
The Architect may ask the Contractors to
remove any of its employees, if not found suitable for work
or desirable to be on the site.
-
The Architect and his representatives
will have at all times an access to the works and to the
workshop or shed or other places of the Contractors which is
used in connection with the said work by the Contractors or
their sub-contractors and the Contractors in their
subcontract with the sub-contractors shall make provision to
that effect.
-
The Architect may issue instructions
requiring any variation in the work and if the Contractors
have done any variation on their own, the Architect may
accept the same if it is complimentary to the work of
construction.
-
Royalties to be paid by contractors :
All royalties or other sums payable in respect of the
supply and use of materials for carrying out the works as
described by or referred to in the contract bills of any
patented articles, processes or inventions shall be deemed to
have been included in the contract sum, and the Contractors
shall indemnify the Company from and against all claims,
proceedings, damages, costs and expenses which may be brought
or made against the Company or to which it may be put to by
reason of the Contractors infringing or being held to have
infringed any patent rights in relation to any such articles,
processes and inventions. PROVIDED that, where in compliance
with Architect’s instructions the Contractors shall supply and
use in carrying out the works, any patented articles,
processes or inventions, the Contractors shall not be liable
in respect of any infringement or alleged infringement of any
patent rights in relation to any such articles, processes and
inventions and all royalties damages or other monies which the
Contractors may be liable to pay to the persons entitled to
such patent rights shall be added to the contract sum.
-
Clerk of the works : The Company
shall be entitled to appoint a clerk of works whose duty shall
be to act solely as Supervisor on behalf of the Company under
the directions of the Architect, and the Contractors shall
afford every reasonable facility for the performance of that
duty. If any directions are given to the Contractors or to
their foreman upon the works by the clerk of the works the
same shall be of no effect unless given in regard to a matter
in respect of which the Architect is expressly empowered by
these conditions to issue instructions and unless confirmed in
writing by the Architect within two working days of their
being given. If any such directions are so given and confirmed
then as from the date of confirmation they shall be deemed to
be the Architect’s instructions.
-
Variations to be measured and valued :
All variations required by the Architect or subsequently
sanctioned by him in writing and all work executed by the
Contractors for which provisional sums are included in the
contract bills shall be measured and valued by the quantity
surveyor who shall give to the contractors an opportunity of
being present at the time of such measurement and of taking
such not and measurements as the Contractors may require. The
valuation of variations and of work executed by the
Contractors for which a provisional sum is included in the
contract bills (other than work for which a tender has been
accepted as aforesaid) unless otherwise agreed shall be made
in accordance with the following rules.
-
The prices in the contract bills shall
determine the valuation of work of similar character
executed under similar conditions as the work priced
therein.
-
The said prices, where work is not of a
similar character or executed under similar conditions as
aforesaid, shall be the basis of prices for the same so far
as may be reasonable, failing which a fair valuation thereof
shall be made.
-
Where work cannot properly be measured
and valued the Contractors shall be allowed day work rates
on the prices prevailing when such work is carried out
(unless otherwise provided in the contract bills)
-
at the rates, if any, inserted by the
Contractors in the contract bills or in the form of
tender, or
-
when no such rates have been inserted,
at the rates fixed by the Architects’ Association.
PROVIDED that in any case vouchers specifying the time
daily spent upon the work (and if required by the
Architect the workmen’s names) and the materials employed
shall be delivered for verification to the Architect or
his authorised representative not later than the end of
the week following that in which the work has been
executed.
-
The prices in the contract bills shall
determine the valuation of items omitted, provided that, if
omissions substantially vary the conditions on which any
remaining items of work are carried out, the prices for such
remaining items shall be valued under sub-clause (b) above.
-
Loss due to variations to be compensated
: If upon written application being made to him by the
Contractors the Architect is of the opinion that a variation
or the execution by the Contractors of any work for which a
provisional sum is included in the contract bills has involved
the Contractors in direct loss and/or expense for which they
would not be reimbursed by payment in respect of a valuation
made in a accordance with the provisions contained in clause
16 above and if the said application is made within a
reasonable time of the loss or expense having been incurred,
then the Architect shall either himself ascertain or shall
instruct the quantity surveyor to ascertain the amount of such
loss or expense. Any amount from time to time so ascertained
shall be added to the contract sum, and if an interim
certificate is issued after the date of ascertainment any such
amount shall be added to the amount which would otherwise be
stated as due in such certificate.
-
What is variation : The term
"variation" used in clauses 16 and 17 means the alteration or
modification of the design, quality or quantity of the works
as shown upon the contract drawings and described by or
referred to in the contract bills, and includes the addition,
omission or substitution of any work, the alteration of the
kind or standard of any of the materials or goods to be used
in the works, and the removal from the site of any work
materials or goods executed or brought thereon by the
Contractors for the purposes of the works other than work
materials or goods which are not in accordance with this
contract.
-
Quality and quantity a per
specifications : The quality and quantity of the work
included in the contract sum shall be deemed to be that which
is set out in the specifications and bills of quantities. Any
error in description or in quantity or in omission of items
from the specifications and bills of quantities shall not
vitiate this contract but shall be corrected and deemed to be
a variation required by the Architect.
-
Not to remove materials : Unfixed
materials and goods intended for, delivered to, and placed on
or adjacent to the works shall not be removed except for use
upon the works unless the Architect has consented in writing
to such removal and which consent shall not be unreasonably
withheld. Where the value of any such materials or goods has
been included in any interim certificate under which the
Contractors have received payment, such materials and goods
shall become the property of the company, but subject to any
other clause applicable and the Contractors shall remain
responsible for loss or damage to the same.
-
Certificate of completion : When in
the opinion of the Architect the works are practically
completed, he shall forthwith issue a certificate to that
effect and practical completion of the works shall be deemed
for all purposes of this contract to have taken place on the
day named in such certificate.
-
Defects to be rectified : Any
defects bad workmanship or other faults which shall appear
during the progress of the work or within the defects
liability period stated in the Appendix ‘D’ to these
conditions and which are due to materials or workmanship not
being in accordance with this contract shall be specified by
the Architect in a schedule of defects which he shall deliver
to the Contractors not later than 14 days from the detection
of such defect or shrinkage or other fault or not later than
14 days after the expiration of the said defects, liability
period, as the case may be and within a reasonable time after
receipt of such schedule the defects, bad workmanship and
other faults therein specified shall be made good by the
contractors and (unless the Architect shall otherwise
instruct, in which case the contract sum shall be adjusted
accordingly) entirely at their own cost.
-
Certificate as to removal defects :
When in the opinion of the Architect any defects, bad
workmanship or other faults which may have required to be made
good under clause 22 above mentioned shall have been made good
he shall issue a certificate to that effect, and completion of
making good the defects shall be deemed for all the purposes
of this contract to have taken place on the day named in such
certificate.
-
No assignment or subletting of Contract
: The Contractors shall not without the written consent of
the Company assign or sublet this contract. (which consent
shall not so far as subletting is concerned by unreasonably
withheld so as to cause prejudice of the Contractor).
-
Indemnity by Contracts : The
Contractors shall be liable for, and shall indemnify the
Company against any liability, loss, claim or proceedings
whatsoever arising under any statute or at common law in
respect of any damage to any property or in respect of any
damage to any property or in respect of personal injury to or
the death of any person whomsoever arising out of or in the
course of or caused by the carrying out of the works, unless
it is due to any act or neglect of the Company or of any
person for whom the Company is responsible.
-
Insurance : Without prejudice to
their liability to indemnify the Company as aforesaid the
Contractors shall maintain and shall cause any sub-contractors
to maintain such insurances as are necessary to cover the
liability of the Contractors or, as the case may be, of such
sub-contractors in respect of any damages, personal injuries
or deaths arising out of or in the course of or caused by the
carrying out of the works, and caused by any negligence
omission or default of the Contractors, their servants or
agents or, as the case may be, of such sub-contractors their
servants or agents.
-
Policies to be produced : The
contractors shall produce or cause any sub-contractors to
produce for inspection the relevant policy or policies of
insurance together with the receipts in respect of premiums
paid under such policy or policies as and when may required so
to do by the company PROVIDED ALWAYS that as and when may be
reasonably required by the company the production by the
Contractors or any sub-contractor of a current certificate of
insurance from the insurance company which shall have issued
the policy or policies aforesaid shall be a good discharge of
the Contractors’ obligation to produce or to cause the
production of the policy or policies and the receipts in
respect of premiums paid.
-
Default in insurance : Should the
Contractors or any sub-contractor make default in insuring or
in continuing to insure as provided above, the Company may
itself insure against any risk with respect to which the
default shall have occurred and may deduct a sum equivalent to
the amount paid in respect of premiums from any monies due or
to become due to the Contractors.
-
Risks for insurance : The
Contractors shall in the joint names of the Company and the
Contractors insure against loss and damage by fire, storm,
tempest, lightning, flood, earthquake, accident, riot and
civil commotion for the full value thereof and all work
executed and all unfixed materials and goods intended for,
delivered to, and placed on or adjacent to the works, but
excluding temporary buildings, plant, tools and equipment
owned or hired by the Contractors or any sub-contractor, and
shall keep such work, materials and goods so insured until the
completion of the works. Such insurance shall be with insurers
approved by the Company and the Contractors shall deposit with
the Company policy or policies and the receipts in respect of
premiums paid and should the Contractors make default in
insuring or continuing to insure as aforesaid the Company may
itself insure against any risk with respect of which the
default shall have occurred and deduct a sum equivalent to the
amount paid by him in respect of premiums from any monies due
or to become due to the Contractors.
-
Damage to be restored on receiving
insurance claim : Upon settlement of any claim under the
insurance aforesaid the Contractors with due diligence shall
restore the work damaged, replace or repair any unfixed
materials or goods which have been destroyed or injured,
remove and dispose of any debris and proceeds with to carry
out and complete the works. All monies received from such
insurances shall be paid to the Contractors by instalments
under certificates of the Architect issued at the periods of
interim certificates named in the appendix to these
conditions. The Contractors shall not be entitled to any
payment in respect of the restoration of work damaged, the
replacement and repair of any unfixed materials or goods, and
the removal and disposal of debris other than the monies
received under the said insurances.
-
Date of possession : Possession of
the site shall be given to the Contractors on the date
mentioned in the Appendix D hereto to annexed and the
Contractor shall thereupon begin the works and regularly and
diligently proceed with the same, and who shall complete the
same on or before the date for completion stated in the said
Appendix D subject nevertheless to the provisions for
extension of time contained in clause 33 of this contract.
-
Compensation for delay : If the
contractors fail to complete the works by the date for
completion stated in the Appendix D to this contract or within
any extended time fixed under clause 33 appearing next and the
Architect certifies in writing that in his opinion the same
ought reasonably so to have been completed, then the
Contractors shall pay or allow to the Company a sum calculated
at the rate stated in the said Appendix D as liquidated and
ascertained damages for the period during which the works
shall so remain or have remained incomplete and the Company
may deduct such sum from any monies due or to become due to
the Contractors under this contract.
-
Extension of time : If the progress
of the works is expected to be delayed, the Contractors shall
forthwith give written notice of the cause of the delay to the
Architect, and if in the opinion of the Architect the
completion of the works is likely to be or has been delayed
beyond the date for completion stated in the said Appendix D
or beyond any extended time previously fixed under either this
clause or any other clause of this contract (a) by force
majeure, or (b) by reason of any excessive rains or fire or
accident (c) by reason of civil commotion, or riots, strike or
lockout affecting any of the trades employed upon the works or
any of the trades engaged in the preparation, manufacture or
transportation of any of the goods or materials required for
the works, or, (d) by reason of the Architect’s instructions
issued under any of the clauses herein or (e) by reason of the
contractors not having received in due time necessary
instruction, drawings, details or levels from the Architect
for which they had applied in writing whether a reasonable
time having regard to the date for completion or (f) by delay
on the part of any nominated sub-contractor or nominated
suppliers and which the Contractors have taken all practicable
steps to avoid or reduce, or (g) by reason of the opening up
for inspection of any work covered up or of the testing of any
of the work materials or goods (including making good in
consequence of such opening up or testing) unless the
inspection or test showed that the work materials or goods
were not in accordance with this contract, or (h) by the
Contractor’s inability for reasons beyond their control and
which they could not reasonably have foreseen at the date of
this contract to secure such labour, goods or materials as are
essential to the proper carrying out of the works then the
Architect shall so soon as they are able to estimate the
length of the delay beyond the date or time aforesaid make in
writing a fair and reasonable extension of time for completion
of the works.
PROVIDED ALWAYS THAT, the Contractors shall use constantly
their best endeavours to prevent delay and shall do all that
may reasonably be required to the satisfaction of the
Architect to proceed with the works.
-
Delay to be compensated : (1) If
upon written application being made to him by the Contractors
the Architect due to any of the causes mentioned in sub-clause
(2) of this clause, is of the opinion that the Contractors
have been involved in direct loss and/or expense for which
they would not be reimbursed by a payment made under any other
provision in this contract by reason of the regular progress
of the works or of any part thereof having been materially
affected by any of the said clauses and if the written
application is made within a reasonable time of it becoming
apparent that the progress of the works of any part thereof
has been affected as aforesaid, then the Architect shall
either himself ascertain or shall instruct the quantity
surveyor to ascertain shall be added to the contract sum, and
if an interim certificate is issued after the date of
ascertainment, any such amount shall be added to the amount
which would otherwise be stated as due in such certificate.
(2) The causes above referred to are (a) the Contractors not
having received in due time necessary instruction, drawings,
details or levels from the Architect for which they had
specifically applied in writing on a date which having regard
to the date for completion stated in the Appendix D to this
contract or to any extension of time then fixed hereunder was
neither unreasonably distant from nor unreasonably close to
the date on which it was necessary for them to receive the
same, or (b) the opening up for inspection of any work covered
up or the testing of any of the work materials or goods was
not in accordance with this contract, or (c) any discrepancy
in or divergence between the contract drawings and / or the
contract bills, (3) The provisions of this clause are without
prejudice to any other rights and remedies which the
Contractors may possess.
-
Consequences of default : If the
Contractors shall (a) without reasonable, cause wholly suspend
the carrying out of the works before completion thereof, or
(b) fail to proceed regularly and diligently with the works,
or (c) refuse or persistently neglect to comply with a written
notice from the Architect requiring them to remove defective
work or improper materials or goods and by such refusal or
neglect the works are materially affected, or (d) fail to
comply with the provisions of clause 24 of this contract
therein and in any of these events the Architect may give to
them a notice by registered post or recorded delivery
specifying the default, and if the Contractors either shall
continue such default for 14 days after receipt of such notice
or shall at any time thereafter repeat such default (whether
previously repeated or not) then the Company without prejudice
to any other rights or remedies, may within 10 days after such
continuance or repetition by registered post or recorded
delivery forthwith determine the employment of the Contractors
under this contract.
-
Automatic determination of contract :
In the event of the Contractors becoming insolvent or making a
composition or arrangement with their creditors or a receiver
or manager of their business or undertaking being appointed,
or possession taken by or on behalf of any secured creditor of
any property comprised in or subject to the charge, or if the
Contractors partnership is dissolved or all the present
partners thereof cease to be partners of their firm the
employment of the contractors under this contract shall be
forthwith automatically determined.
-
Consequences of determination by Company :
In the event of the employment of the Contractors being
determined as aforesaid and so long as it has not been
reinstated and continued, the following shall be the
respective rights and duties of the Company and Contractors
namely (a) the Company may employ and pay other persons to
carry out and complete the works and he or they may enter upon
the works and use all temporary buildings, plant, tools,
equipment, goods and materials intended for, delivered to and
placed on or adjacent to the works, and may purchase all
materials and goods necessary for the carrying out and
completion of the works. (b) the Contractors shall, if so
required by the Company or the Architect within 14 days of the
date of determination, assign to the company without payment,
the benefit of any agreement for the supply of materials or
goods and/or for the execution of any work for the purposes of
this contract. The Company may pay any such supplier or
sub-contractor for any materials or goods delivered or works
executed for the purposes of this contract (whether before or
after the date of determination) insofar as the price thereof
has not already been paid by the contractors. The Company’s
rights under this clause are in addition to its rights to pay
nominated subcontractors as provided in this contract and
payments made under this clause may be deducted from any sum
due or to become due to the Contractor. (c) the Contractors
shall as and when required in writing by the Architect so to
do (but not before) remove from the works any temporary
building, plant, tools, equipment, goods and materials
belonging to or hired by them. If within a reasonable time
after any such requirement has been made the Contractors have
not complied therewith, then the company may (but without
being responsible for any loss or damage) remove and sell any
such property of the Contractors and shall hold the proceeds,
less all costs incurred, to the credit of the Contractors, (d)
the Contractors shall allow or pay to the Company in the
manner hereinafter appearing the amount of any direct loss
and/or damage caused to the Company by the determination.
Until after completion of the works under sub-clause (a) of
this clause the Company shall not be bound by any provision of
this contract to make any further payment to the Contractors,
but upon such completion and the verification within a
reasonable time of the accounts therefor the Architect shall
certify the amount of expenses properly incurred by the
Company and the amount of any direct loss and/or damage caused
to the Company by the determination and, if such amounts when
added to the monies paid to the Contractors before the date of
determination exceed the total amount which would have been
payable on completion in accordance with this contract, the
difference shall be a debt payable to the Company by the
Contractors, and if the said total amount when added to the
said monies be less than the said total amount the difference
shall be a debt payable by the Company to the Contractors.
-
Contractors right to determine : The
Contractors may, by notice in writing and sent to the company
by registered post determine their contract in any of the
following event namely :
-
If the Company does not pay to the
Contractors the amount due on any certificate within the
period for honouring certificates named in the said Appendix
D and continue such default for 7 days after the receipt by
registered post of a notice from the Contractors stating
that notice of determination under this condition will be
served if payment is not made within 7 days from receipt
thereof, or
-
The Company interferes with or obstructs
the issue of any certificate due under this contract, or
-
The carrying out of the whole or
substantially the whole of uncompleted works, is suspended
for a continuous period of the length named in the said
Appendix by reason of loss or damage occasioned by any one
or more of the contingencies referred to in clause 33 (if
applicable),
-
The Company makes a composition or
arrangement with its creditors or has a winding up order
made or (except for the purposes of reconstruction) a
resolution for voluntary winding up passed or a receiver or
manager of its business or undertaking is duly appointed, or
possession is taken by or on behalf of the holders of any
secured debentures of any mortgaged property of the Company.
-
Consequence of determination by contracts :
Upon such determination, by the Contractors as aforesaid,
and without prejudice to the accrued rights or remedies of
either party or to any liability of the classes mentioned in
clause 25 of his contract the respective rights and
liabilities of the Contractors and the Company shall be as
follows, that is to say :
-
The Contractors shall with all reasonable
dispatch and in such manner and with such precautions as
will prevent injury, death or damage of the classes in
respect of which before the date of determination he was
liable to indemnify the Company under this contract remove
from the site all his temporary buildings, plant, tools,
equipment, goods and materials and shall give facilities for
his sub-contractors to do the same, but subject always to
the provision of item (iv) of sub-clause (b) of this clause.
-
After taking into account amounts
previously paid under this contract the Contractors shall be
paid by the Company,
-
The total value of work completed at
the date of determination.
-
The total value of work begun and
executed but not completed at the date of determination,
the value being ascertained in accordance with clause 16
of this contract as if such work were a variation required
by the Architect.
-
Any sum ascertained in respect of
direct loss and/or expense under clauses 17 and 34 of this
contract (whether ascertained before or after the date of
determination).
-
The cost of materials or goods properly
ordered for the works for which the Contractors shall have
paid or for which the Contractors are legally bound to
pay, and on such payment by the Company any materials or
goods so paid for shall become the property of the
Company.
-
The reasonable cost of removal under
sub-clause (a) of this clause.
-
Any direct loss and/or damage caused to
the Contractors by the determination.
PROVIDED that in addition to all other remedies, the
Contractors upon such determination may take possession of
and shall have a lien upon all unfixed goods and
materials, which may have become the property of the
Company under this contract until payment of all monies
due to the Contractors from the Company.
-
Company’s right to do other works : The
Contractors shall permit the execution of work not forming
part of this contract by artists, tradesmen or others engaged
by the Company. Every such person shall be deemed to be a
person for whom the Company is responsible and not to be a
sub-contractor.
Certificate for payment :
-
At the period of interim certificates
named in the appendix D to this contract the Architect shall
issue a certificate stating the amount due to the
Contractors from the Company and the Contractors shall, on
presenting any such certificate to the Company, be entitled
to payment therefor within the period for honouring
certificates named in the appendix to the contract. Interim
valuations shall be made whenever the Architect considers
them to be necessary for the purpose of ascertaining the
amount to be stated as due in a interim certificate.
-
The amount stated as due in an interim
certificate shall be the total value of the work properly
executed and of the materials, and goods delivered to or
adjacent to the works for use thereon up to and including a
date not more than 7 days before the date of the said
certificate less any amount which may be retained by the
Company (as provided in sub-clause (3) of this clause) and
less any instalments previously paid under this contract.
PROVIDED that such certificate shall only include the value
of the said materials and goods as and from such time as
they are reasonably, properly and not prematurely brought to
or place adjacent to the works and then only if adequately
protected against weather or other casualties.
-
The Company may retain the percentage of
the total value of the work, materials and goods referred to
in sub-clause (2) abovementioned which is named in the said
Appendix D as percentage of certified value retained.
PROVIDED ALWAYS that when the total sum of the amounts so
retained equals the amount named in the said appendix as
limit of retention fund or that amount as reduced in
pursuance of any clause of this contract, no further amount
shall be retained by virtue of sub-clause.
-
(4) The amounts retained by virtue of
sub-clause (3) of this contract shall be subject to the
following provisions:
-
The Company’s interest in any amounts
so retained shall be fiduciary as trustee for the
Contractors (but without obligation to invest), and the
Contractor’s beneficial interest therein shall be subject
only to the right of the Company to have recourse thereto
from time to time for payment of any amount which they are
entitled to under the provisions of this contract to
deduct from any sum due or to become due to the
Contractors.
-
On the issue of the certificate of
practical completion the Architect shall issue a
certificate for one money of the total amount then so
retained and the Contractor shall, on presenting any such
certificate to the Company, be entitled to payment of the
said money within the period for honouring certificates
name in the said appendix.
-
On the expiration of the defects
liability period named in the said appendix, or on the
issue of the certificate of completion of making good the
defects, whichever is the later, the Architect shall issue
a certificate for the residue of the amounts then so
retained and the Contractors shall, on presenting any such
certificate to the Company, be entitled to payment of the
said residue within the period for honouring certificates
named in the said appendix.
Measurement of valuation
-
The measurement and valuation of the
works shall be completed within the period of final
measurement and valuation stated in the said Appendix D and
the Contractors shall be supplied with a copy of the priced
bills of variation not later than the end of the said period
and before the issue of the final certificate under clause
43 of this contract.
-
Either before or within a reasonable time
after practical completion of the works the Contractors
shall send to the Architect all documents necessary for the
purpose of the computations required by his contract
including all documents relating to the accounts of
sub-contractors and suppliers.
-
In the settlement of accounts the amounts
paid or payable under the appropriate contracts by the
Contractors to sub-contractors or suppliers (including the
discounts if any) the amounts paid or payable by virtue of
clause 41(4) (b) of this contract in respect of fees or
charges for which a provisional sum is included in the
contract bills, the amounts paid or payable in respect of
any insurance maintained in compliance with clause 29 of
this contract and the value of any work executed by the
Contractors for which a provisional sum is included in the
contract bills shall be set against the relevant prime cost
of or provisional sum mentioned in the contract bills, and
the balance after allowing in all cases pro rata for
the Contractor’s profit at the rates shown in the contract
bills, shall be added to or deducted from the contract sum,
PROVIDED that no deduction shall be made in respect of any
damages paid or allowed to the Contractors by any
sub-contractor or supplier.
Final certificate : So soon as is
practicable but before the expiration of 3 months from the end
of the defects liability period stated in the said appendix or
from completion of making good defects under clause 22 of
these conditions or from receipt by the Architect of the
documents referred to in sub-clause (b) of clause 42 of this
contract, whichever is the latest, the Architect shall issue
the final certificate. The final certificate shall state.
Certificate to be conclusive : The
said certificate shall be conclusive evidence in any
proceedings on this contract that the works have been properly
carried out and completed in accordance with the terms of this
contract and that necessary effect has been given to all terms
of this contract which require an adjustment to be made to the
contract sum, except when the certificate is disputed either
by the Company or the Contractors on any of the following
grounds namely (a) that the certificate is vitiated by fraud,
dishonesty or fraudulent concealment relating to the works, or
any part thereof, or to any matter dealt with in the said
certificate, or (b) because of any defect (including any
omission) in the works, or any part thereof which with
reasonable inspection or examination at any reasonable time
during the carrying out of the works or before the issue of
the said certificate would not have been disclosed, or (c)
because of any accidental inclusion exclusion of work,
materials, goods or figure in any computation or any
arithmetical error in any computation.
Contract sum how to be calculated : The
Contract sum shall be deemed to have been calculated in the
manner set out below and shall be subject to adjustment in the
events specified hereunder :
-
The prices (including the cost of
Company’s liability, insurance and third party insurance)
contained in the contract bills are based upon the rates of
wages and other emoluments and expenses (including holiday
credits) payable by the Contractors to work people engaged
upon or in connection with the works in accordance with the
rates in Central P.W.D. Contracts for similar work.
-
If the said rates of wages and other
emoluments and expenses (including holiday credits) shall be
increased or decreased by reason of any alteration in
contract after the said date of tender then the net amount
of the increase or decrease in wages and other emoluments
and expenses (including holiday credits) together with the
net amount of any consequential increase or decrease in the
cost of Company’s liability insurance and third party
insurance shall as the case may be, be paid or allowed by
the Contractors.
-
The rates of building materials given in
the Schedule of rates attached hereto are the current market
rates. If the rates go up by more than 10% or are lowered by
more than 10% then the amount of increase or decrease in the
cost of building material shall be payable to or allowable
by the Contractors accordingly.
Arbitration : In case any dispute or
difference shall arise between the Company or the Architect on
its behalf and the Contractors either during the progress or
after the completion or abandonment of the works as to the
construction of this contract or as to any matter or thing of
whatsoever nature arising thereunder or in connection
therewith (including any matter or thing left by this contract
to the discretion of the Architect or the withholding by the
Architect of any certificate to which the Contractor may claim
to be entitled or the measurement and valuation mentioned in
clause 42 or the rights and liabilities of the parties under
any of the clauses of this contract, then such dispute or
difference shall be and is hereby referred to the arbitrators
of a common Arbitrator if agreed upon or otherwise to two
Arbitrators one to be appointed by each party to the dispute
and the Arbitration shall be governed by the Arbitration Act,
for the time being in force.
Right to appoint sub-contractors :
Notwithstanding anything contained hereinbefore the
Contractors will be entitled to appoint one or more
sub-contractors either for supplying labour, or buying
material or for construction of any work but the contracts
entered by the Contractors with sub-contractors will be
subject to this contract and there will be no private between
the Company and sub-contractor and the Contractors will be
liable and responsible for the acts of omission or commission
of the sub-contractor as if they are their own acts.
IN WITNESS WHEREOF the parties have put
their hands the day and year first hereinabove written.
| SIGNED AND
DELIVERED |
) |
|
| for and On
behalf of the Company |
) |
|
|
___________________ |
) |
|
|
___________________ |
) |
|
| |
|
|
| duly
authorised in that |
) |
|
| behalf in the
presence of |
) |
|
| |
|
|
|
SIGNED by
|
) |
|
| being the
partners |
) |
|
| 1) |
) |
____________________ |
| 2) |
) |
____________________ |
| 3) |
) |
____________________ |
| |
| in the
presence of ______________ |
|
|
|
|